Intelligent Transportation Systems (ITS) - Events/Milestones

Deliverables

Due Date

Purpose

ITS Blueprint Workshop

January 2003

  • Review results of Phase 1
  • Present preliminary recommendations for the Highway 2 corridor.
  • Obtain stakeholder input
Preliminary Blueprint Report April 2003
  • Review of preliminary Blueprint results with Steering Committee
ITS Blueprint Report October 2003
  • Release of report documenting ITS Blueprint recommendations
ITS Blueprint Workshop 2 October 2003
  • Present project findings and recommendations to the stakeholders
Final Presentation January 2004
  • Present final study findings and recommendations to Steering Committee

Study Closure

March 2004

  • Final report and web updates