Stoney Trail / Crowchild Trail Interchange
The Stoney Trail Extension Project will connect Highway 1 (Trans-Canada Highway) to Highway 2 (Deerfoot Trail). When completed it will be a four lane divided roadway located in the northwest quadrant of the city. The project has been divided into various components with varying completion dates. The entire extension is scheduled to be complete in the fall of 2009, weather permitting.
Stantec Consulting has been engaged by Alberta Transportation for the design and construction management of the Crowchild Trail interchange. Associated with the interchange, is the realignment of Tuscany Boulevard and it's connection to Stoney Trail. The Crowchild interchange and the Scenic Acres Link interchange will replace the existing signalized intersections on Stoney Trail at Scenic Acres Link, Tuscany Boulevard and Crowchild Trail. These new interchanges require no traffic signals on Stoney Trail or Crowchild Trail in this area and will provide improved access and safety while reducing travel time.
The City of Calgary has made plans to extend the Northwest LRT line to Rocky Ridge Road along the median of Crowchild Trail. Additional information about the LRT can be found on their web site: Northwest LRT Extension.
Project Completion: Fall 2011
Project Updates
- Project Update - Winter 2009/10 (pdf 32K)
- Project Update - Summer 2009 (pdf 32K)
- Project Update - Winter 2008/09 (pdf 29K)
- Project Update - July 2008 (pdf 171KB)
- Project Update - Spring 2008 (pdf 35K)
- Project Update - Spring 2007 (pdf 19K)
- Project Update - January/February 2006 (pdf 85K)
- Project Update - October 2005 (pdf 71K)
- Project Update - August 2005 (pdf 57K)
- Innovative Planning Means New Interchanges to Stoney Trail - January 2005
Maps
- Crowchild Trail Detour Configuration and Site Plan (pdf 582K)
- Crowchild Trail Interchange Configuration and Site Plan (pdf 1,030K)
- Crowchild Trail to Scenic Acres Link Interchanges Configuration and Site Plan (pdf 1,457K)
- Artistic Rendering - Crowchild Trail and Scenic Acres Link Interchanges (pdf 387K)
- Stoney Trail Extension - Trans-Canada Highway to Country Hills Boulevard (pdf 4,057K)
- Stoney Trail Extension Corridor Plan (pdf 2,329K)
Photos
- Airphoto (Looking Southeast) - May 2009 (pdf 183K)
- Airphoto (Looking Northeast) - May 2009 (pdf 177K)
- Airphoto (Looking Southwest) - October 2008 (pdf 199K)
- Airphoto (Looking North) - October 2008 (pdf 192K)
- Airphoto (Looking Southeast) - September 2008 (pdf 175K)
- Airphoto (Looking Northeast) - September 2008 (pdf 164K)
- Airphoto (Looking North) - July 2008 (pdf 242K)
- Airphoto (Looking Northeast) - July 2008 (pdf 226K)
- Airphoto (Looking North) - June 2008 (pdf 187K)
- Airphoto (Looking East) - June 2008 (pdf 219K)
- Airphoto (Looking Southwest) - September 2007 (pdf 194K)
- Airphoto (Looking North) - September 2007 (pdf 185K)
- Airphoto (Looking Northeast) - September 2007 (pdf 205K)
- Crowchild Trail Airphoto (Looking Northeast) - June 2007
- Crowchild Trail Airphoto (Looking North) - June 2007
- Crowchild Trail Airphoto (Looking West) - September 2006
- Crowchild Trail Airphoto (Looking North) - April 2006
- Crowchild Trail Airphoto (Looking Northwest) - October 2005
- Crowchild Trail Airphoto (Looking Northwest) - September 2005
- Crowchild Trail Airphoto (Looking East) - October 2004
- Crowchild Trail Airphoto (Looking Northeast) - October 2004
Background
- Community Update - Stoney Trail Expansion - November 2004 (pdf 267K)
- Transportation and Utility Corridor Web Page
- Functional Planning Study
- Past Open Houses (pdf 90K)
- Background Information - June 2004 (pdf 60K)
- Frequently Asked Questions (pdf 54K)
For more information on this project, please call (403) 716-8198 or email: transportation.calgary@stantec.com